Redevelopment News
BEMI Services Ltd
Reports
Week Ending 08.08.08 Click Here
Week Ending 03.08.08 Click Here
Week Ending 25.07.08 Click Here
Week Ending 18.07.08 Click Here
Week Ending: 11.07.08 Click Here
Week Ending: 20.06.08 Click Here
Week Ending: 30.05.08 Click Here
Week Ending: 23.05.08 Click Here
Week Ending: 16.05.08 Click Here
Week Ending: 09.05.08 ClickHere
Week Ending: 02.05.08 Click Here
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension has continued with the plastering to the ceiling and walls.
· Work has continued to the fitting of the skirting to the ground floor areas.
· Work has commenced to the erection of the store areas within the devotional area.
· The arch and gable to the new entrance have been built this week and the hardcore fill to this area has commenced.
· The drainage works to the extension have commenced.
· The fitting of the light fittings and the gas heaters are in progress.

The new front entrance progressing.

The new lift from the top of the stairs.

The new lift at ground floor

The new storage area within the devotional area.
Roy Davis
Clerk of works.
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension has continued with the 2nd fix electrical and mechanical works in progress.
· The glazing to the 1st floor screen has commenced.
· Work has commenced on fitting the skirting to the ground floor areas.
· The floor screed to the extension has been laid this week.
· Work has commenced to the garden walls to the new front entrance.
· The windows to the rear elevation have been glazed.

Glazing to the kitchen windows.

Garden wall to new front entrance.

Screen to 1st floor room glazed

Existing window to small 1st floor room.

Skirting duct detail for heater.

Up/down light fitting in worship area.
Roy Davis
Clerk of works.
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension has continued with the 1st fix electrical and mechanical works in progress.
· Work has continued internally with the partition wall forming the screen to the worship area being constructed and plastered.
· The 1st floor toilet has been tiled.
· The fitting of the stairs is complete.
· Work to both the electrical and heating installations is continuing.

Rear elevation.

The end screen to the first floor.

View towards the choir from the first floor.

The new serving hatch to the kitchen.

Stairs to the first floor.
Roy Davis
Clerk of works.
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension is continued with the roof trusses and decking now fitted.
· The external scaffolding as been removed.
· Work has continued internally with the partition wall forming the screen to the worship area being constructed.
· The fitting of the stairs has commenced
· Work to both the electrical and heating installations is continuing. With the wiring to the extension in progress.

Screen and wall to 1st floor.

The stairs being fitted.

The roof on to the extension.

Rear entrance and windows to the toilet area.
Roy Davis
Clerk of works.
Week Ending: 28.03.08
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension is continuing with the roof trusses and decking being fitted.
· The opening to the new front entrance has been formed.
· Work has continued internally with the partition walls forming the 1st floor rooms. These have been plastered along with the ceiling to the main hall.
· The preparation work ready for the fitting of the stairs has continued with the scaffolding to the tower being removed now that the new access ladder has been installed.
· Work to both the electrical and heating installations is continuing.
· Some light fittings to the first floor rooms have been installed.

The opening for the new main entrance.

The old entrance doors being opened for the last time.

The roof to the new extension being installed.

The main hall looking towards the devotional area.
Roy Davis
Clerk of works.
Week Ending: 21.03.08
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Actual Start: 14.01.08
Contract Period:
Contract completion date:
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
The work to the extension is continuing with the
Wall plate and roof trusses being fitted.
The foundations to the new front entrance have been concreted.
Work has continued internally with the partition walls forming the 1st floor rooms are being plastered along with the ceiling to the main hall.
The preparation work ready for the fitting of the stairs as commenced.
Work to both the electrical and heating installations is continuing.
The new access ladder to the tower is being fitted.

The screens forming the corridor

The roof to the extension commences.

Foundations to the new entrance.
Week Ending: 14.03.08
Clerk of Works Weekly Report
Architect: PB. Associates.
General Contractor R&V Taylor Ltd.
Actual Start: 14.01.08
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
The work to the extension is continuing with the brick and block work now up to wall plate height.
The foundations to the new front entrance have been concreted.
Work has continued internally with the partition walls forming the 1st floor rooms have been boarded.
Work to both the electrical and heating installations is continuing.

The rear elevation of the extension.

The new rear entrance door opening.

Entrance screen into the large 1st floor room.

Back wall to the large 1st floor room.

1st floor corridor looking towards the disabled toilet.

Library from the doorway.
Clerk of Works Weekly Report
Architect: PB. Associates. General Contractor R&V Taylor Ltd. Actual Start: 14.01.08 Contract Period: Contract completion date:
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension is continuing with the stone work to the windows now complete and brick and block work up to window head height.
· The foundations to the new front entrance are now ready for concreting.
· Work has continued internally with the framing to the roof supports being completed.
· The partition walls forming the 1st floor rooms are in progress and are nearly ready for boarding.
· Work to both the electrical and heating installations is continuing.
· The roof repairs to the tower have been carried out this week. (Note this is not part of the contract works)

New stone arches to windows.
Stud partition walls to rooms to the 1st floor.

Partition Walls 1st Floor.
Foundations to the new main entrance.
Roy Davis
Clerk of Works
BEMI Services Ltd
Clerk of Works Weekly Report
Architect: PB. Associates. General Contractor R&V Taylor Ltd.
Actual Start: 14.01.08
Contract Period: Contract completion date:
Progress of work and remarks including urgent requirements.
Set out below the main elements of work carried out, or being carried
out.
· The work to the extension is continuing with the stonework to the windows.
· The internal work is continuing with the flooring to the 1st floor complete.
· The glulam framework to support the roof adjacent to the tower is also near completion.
· The frames to form the corridor to the lift and stairs have been fitted.
· The stairs have been delivered to site.
· The preparation for cutting and forming the new openings is in progress.
· Work to both the electrical and heating installations is continuing.
· Work has commenced to the new front entrance with the removal of the vegetation and excavation of the wall foundations.

Frames to corridor.

Support posts to the roof adjacent to the tower.

Stone jambs and mullions to windows.

New main entrance.
Roy Davis
Clerk of works.